top of page
Writer's pictureStanley Eisen

Update


Another beautiful Pompano sky!


Update

1-Stack 4 is done with the exception of railing adjustments. The railing sub-contractor has been problematic about showing up. 3 Board members, who meet every week with the main contractor and our engineer, have sent the sub-contractor a serious threat regarding this issue. There is NO concern by our engineer regarding the railing’s safety, but this contractor is holding up our progress and the speed at which our project can progress. He is due to show up in a few days for a “meeting of the minds” with us, our main contractor and the engineer. To be continued…………


2-Stack 5 is up to railings and glass adjustments.


3-Stack 6 railings are installed, but need adjustments.


4-Stack 7 is moving along. As doors are replaced, several more are taken out. This process is making the procedure go much faster than it was under our old foreman.


5-Stack 7 will be ready for railing installation the beginning of April.


6-The second floor parking deck will be started as soon as stack 6 is done and the swing stage is removed from over the parking deck.


7-The roof of the Wet Room is STILL waiting for the city to give us a permit to apply the roof.

16 views0 comments

Recent Posts

See All

Spring Farewell Party

Friday, April 12th, at 5pm Pool Cabana Room You are all invited to our farewell party for the seasonal residents that will be flying...

Comments


bottom of page