This update will be the last one until the New Year. With the holidays coming up there will not be that many work days.
1-Excavations will be continuing on stack 1. They will be continuing for a while.
2-Stack 2 is at a standstill for now. It is anticipated that the swing stage on the 7/8 stack windows will be moved to stack 2 after New Years. It is now being used to clean windows and finish up last minute stucco touch ups. Ruined screens will be re-screened.
3-Stack 8 is continuing with the removal of doors and the concrete around them.
4-The 8 stack is being problematic in that until it is completed, the finishing of the pool and pool deck cannot be worked on with debris falling on the pool deck and anyone who would be working there. It is hoped that 8 stack will be completed by the beginning of March so that the pool area, the pool and the wet room can be finished off.
We hope everyone enjoys Christmas, New Years and any holidays you may celebrate. Stay healthy and let's hope for a wonderful New Year.