top of page

The Latest Update


Another new day in Pompano!


Today’s Updates!


1-Railing adjustments were made on stack 5 and are now being inspected. Glass repairs are also continuing on stack 5.


2-Stack 4 railing adjustments were more problematic. If stack 5’s repairs meet the inspection requirements, then stack 4 railing adjustments will follow.


3-Touch ups will then have to be made to the balcony’s decks.


4-Stack 6 has shutter reinstallation continuing.


5-Stack 7 had concrete placement going on. Several more doors are being inspected and hopefully put back in place.


6-Stack 8 is in the process of having its steel cleaned.


7-Excavation is continuing on the second floor parking deck.


8-Exterior repairs of the pool structure are completed. Deck and interior repairs must wait until stacks 7 and 8 are complete so that no debris can fall on men working there.


9-Going forward our contractors tell us that stack 5 should be done in a few weeks. Stack 4 should be done about the same time and stack 6 shortly after that. Then the second floor parking area will be under construction.


Stan

4 views0 comments

Recent Posts

See All

Spring Farewell Party

Friday, April 12th, at 5pm Pool Cabana Room You are all invited to our farewell party for the seasonal residents that will be flying...

Comments


bottom of page