Another new day in Pompano!
Today’s Updates!
1-Railing adjustments were made on stack 5 and are now being inspected. Glass repairs are also continuing on stack 5.
2-Stack 4 railing adjustments were more problematic. If stack 5’s repairs meet the inspection requirements, then stack 4 railing adjustments will follow.
3-Touch ups will then have to be made to the balcony’s decks.
4-Stack 6 has shutter reinstallation continuing.
5-Stack 7 had concrete placement going on. Several more doors are being inspected and hopefully put back in place.
6-Stack 8 is in the process of having its steel cleaned.
7-Excavation is continuing on the second floor parking deck.
8-Exterior repairs of the pool structure are completed. Deck and interior repairs must wait until stacks 7 and 8 are complete so that no debris can fall on men working there.
9-Going forward our contractors tell us that stack 5 should be done in a few weeks. Stack 4 should be done about the same time and stack 6 shortly after that. Then the second floor parking area will be under construction.