Another beautiful day to go fishing or do anything outdoors!


Updates


1-Stack 4 glass scratch removal is almost complete.


2-Stack 6-Balcony basecoat will be inspected. Railing are now due for installation.


3-Stack 3-The last few floor touch ups will be scheduled.


4-Stack 7-Doors are inspected as they are replaced, then a few more are removed. Upon completion they will all be water tested.


5-All tiles are removed from stack 8 and the bad concrete has been marked for excavation.


6-The pool was drained again while we try to figure out why it keeps cracking. The structure may need to be stabilized.


7-The wet room roof is STILL waiting for a Pompano permit.