The weather has not been sunny and gorgeous! The weather in 3 words are rain, thunder and lightening, all of which have had an affect on the speed of our project.
1-News-We voted Orkin off the island! The new exterminator is Terminex who is starting today. They are a bit less expensive and included more services. We also have them installing electronic bug whackers at the 2 doors on the second floor which has had a mosquito issue.
2-Stacks 4 and 5 are done except for 2 units which are waiting for the glass contractor. Ali is now sending out the questionnaire for those owners to list any issues they have inside their units.
3-Stack 6 has final touch ups being done before the inspector is scheduled. This should not take long.
4-Stack 7 is now having balconies waterproofed and stuccoed. Unfortunately, neither one can be done in the rain. That is holding us up.
5-The bedroom windows on stack 7, from floors 1 to 6 are done. The next 6 floors are scheduled to begin tomorrow, weather permitting.
6-Concrete is being place on 5 of the balconies on stack 8. There are 3 more balconies on this stack that need to be excavated.
7-The front of the building, 8 stack windows are being inspected today so that concrete can be replaced.
8-The second floor of the parking deck unexpectedly became an issue beyond all of our control. The contractor and engineer found a satisfactory coating. Due to all of the supply chain issues caused by covid it is not available in the quantity we need. Sooooo, our contractor found a comparable product from another company. We are just waiting for the engineer to review the specifications to see if it is acceptable to them.
9-Now for the National Sport of Pompano, waiting for the Department of Buildings! We are still waiting for the permit for the roof of the wet room. The contractor is trying, AGAIN, to find out what the delay is. I think it may be easier to get information from the Pentagon!
Everyone please stay safe.
Stan